Semiconductor

CASE-2024-06

JIANGSU, CN

12-Inch Wafer Fab Ultrapure Water System — East China

Full-chain UPW delivery for a 12-inch logic fab, covering source water analysis, process design (PFD/P&ID), in-house equipment manufacturing, on-site installation and 30-day FAT/SAT acceptance. Two years of continuous operation with resistivity stable above 18.2 MΩ·cm at point-of-use.

DESIGN CAPACITY

45m³/h

OUTPUT RESISTIVITY

18.2 MΩ·cm

TOC AT POU

< 1 ppb

Process

8-Stage UPW

UPW Skid Hall
PROJECT SITE · UPW SKID HALL
Pre-treatment, 2-pass RO, EDI, mixed-bed polishing and UPW distribution loop, all in-house manufactured.
◆ Project Fact Sheet
At a Glance
8 KEY DATA POINTS
Industry
Semiconductor
Location
JIANGSU, CN
Capacity
70 m³/h
Scope
Full Turnkey
Process
8-Stage UPW
Delivery
180 Days
Commissioned
2024-03
Status
◆ Normal Operation
§ 01 — Project Background

Why this project demanded a turnkey UPW partner

The client is a major foundry operating a newly built 12-inch logic wafer fab for advanced process nodes. Their wet etch and rinse stations required SEMI-grade ultrapure water with strict particle, TOC and metallic ion specifications — water quality that directly determines wafer yield.

Rather than splitting the project across an equipment vendor and a separate engineering firm, the client chose Hongjie Water as a single turnkey partner covering process design (PFD/P&ID), in-house manufacturing, on-site installation, FAT/SAT testing, and long-term O&M support.

§ 02 — Engineering Challenges

Four constraints we had to solve in parallel

CHALLENGE / 01

Variable Source Water

Municipal source water with seasonal fluctuation in turbidity, hardness and TOC. Required adaptive pre-treatment that wouldn't compromise downstream RO membrane life.

CHALLENGE / 02

Sub-ppb TOC Target

Logic process required total organic carbon < 1 ppb at point-of-use, demanding UV oxidation + polishing mixed-bed configuration with 365 nm / 185 nm dual-wavelength control.

CHALLENGE / 03

Distribution Loop Integrity

2.4 km of PVDF loop with 36 point-of-use drops, each requiring particle count < 5/mL at 0.05 µm. Loop velocity, dead-leg control and material certification all critical.

CHALLENGE / 04

Tight Commissioning Window

Client's tool move-in schedule allowed only 21 days for FAT/SAT acceptance. Required pre-validated skid manufacturing and parallel on-site testing protocols.

§ 03 — Process Design

The full-chain UPW process we deployed

Eight sequential stages from raw source water to point-of-use, with measurement instruments at every critical handoff. Each stage was sized and validated for the fab's projected 5-year capacity ramp.

◆ Full Process Chain — 8 Stages

Source Water → Point-of-Use Delivery

PFD · REV-04 · 2024.02
/ 01
Pre-treatment
MMF + ACF
/ 02
1st-Pass RO
Conductivity ↓
/ 03
2nd-Pass RO
Polish RO
/ 04
EDI
Continuous Deion.
/ 05
UV 185nm
TOC Oxidation
/ 06
Mixed Bed
Final Polish
/ 07
UF Filtration
0.05 µm cutoff
/ 08
POU Loop
36 Drops
§ 04 — Technical Specifications

Designed targets vs. measured performance

All measurements taken at the production loop after 30 days of continuous operation. Continuously monitored values reported as 24-hour average ± deviation.

Parameter
Designed Spec
Measured Value
Status
Resistivity @ 25°C
≥ 18.0 MΩ·cm
18.25 MΩ·cm
Pass
TOC (point-of-use)
< 2.0 ppb
0.8 ppb
Pass
Particle Count (≥0.05 µm)
< 10 / mL
3 / mL
Pass
Bacteria (CFU)
< 1 / 100 mL
0 / 100 mL
Pass
Metallic Ions (Na, K, Fe)
< 1 ppt each
< 0.5 ppt
Pass
Dissolved Silica
< 1 ppb
0.4 ppb
Pass
§ 06 — Measured Outcomes

Two years in — the numbers that matter

99.98%
System Uptime over 24 Months
0unplanned
Process Excursions Since SAT
-18%
Operating Cost vs. Original Design
§ 07 — Client Feedback

In the client's words

Hongjie's team delivered exactly what they specified in the PFD — no surprises during commissioning, no rework on the loop, and TOC measurements have stayed well below our internal alarm threshold for two years running. Their on-site engineers became part of our maintenance team.

FE
Facilities Engineering Director
12-INCH WAFER FAB · EAST CHINA
◆ READY TO START YOUR PROJECT

Building a similar UPW system?

Share your source water report — our process engineers will respond within 24 hours with a tailored process recommendation and reference projects matching your industry and capacity requirements.

Get a Quote

Thank you for your trust; we will respond to your enquiry within 24 hours.

No spam, only technical feedback
Response within 24 hours
Used by semiconductor, pharma & battery industries

Get Your Water Report → PFD in 24 Hours

Our engineers will analyze your water report and provide a tailored PFD solution.

No spam, only technical feedback
Response within 24 hours Used by semiconductor, pharma & battery industries