The client is a major foundry operating a newly built 12-inch logic wafer fab for advanced process nodes. Their wet etch and rinse stations required SEMI-grade ultrapure water with strict particle, TOC and metallic ion specifications — water quality that directly determines wafer yield.
Rather than splitting the project across an equipment vendor and a separate engineering firm, the client chose Hongjie Water as a single turnkey partner covering process design (PFD/P&ID), in-house manufacturing, on-site installation, FAT/SAT testing, and long-term O&M support.
Municipal source water with seasonal fluctuation in turbidity, hardness and TOC. Required adaptive pre-treatment that wouldn't compromise downstream RO membrane life.
Logic process required total organic carbon < 1 ppb at point-of-use, demanding UV oxidation + polishing mixed-bed configuration with 365 nm / 185 nm dual-wavelength control.
2.4 km of PVDF loop with 36 point-of-use drops, each requiring particle count < 5/mL at 0.05 µm. Loop velocity, dead-leg control and material certification all critical.
Client's tool move-in schedule allowed only 21 days for FAT/SAT acceptance. Required pre-validated skid manufacturing and parallel on-site testing protocols.
Eight sequential stages from raw source water to point-of-use, with measurement instruments at every critical handoff. Each stage was sized and validated for the fab's projected 5-year capacity ramp.
All measurements taken at the production loop after 30 days of continuous operation. Continuously monitored values reported as 24-hour average ± deviation.
From signed PO to SAT acceptance: 180 days total. In-house manufacturing of all primary skids in our Wuxi facility (60 days), parallel site preparation, on-site installation (35 days), factory acceptance test (FAT, 14 days) and site acceptance test (SAT, 21 days).
UPW PRIMARY SKID
SCADA / CONTROL
ON-SITE INSTALL
FAT TESTINGHongjie's team delivered exactly what they specified in the PFD — no surprises during commissioning, no rework on the loop, and TOC measurements have stayed well below our internal alarm threshold for two years running. Their on-site engineers became part of our maintenance team.
Share your source water report — our process engineers will respond within 24 hours with a tailored process recommendation and reference projects matching your industry and capacity requirements.